§ 14.08.100. Inspection—Construction projects.  


Latest version.
  • A.

    Inspection of all sewerage construction or alterations under this chapter shall be made during construction by personnel of the city or its contractor. At least forty-eight hours prior to cutting into a city sewer, the city shall be notified. No physical alteration of any city facility shall commence until an inspector is present. No covering or backfilling of any work shall commence until such work has been inspected.

    B.

    Upon completion of construction and prior to removal of the downstream bulkhead and upon receiving forty-eight hours' notice, Sundays and holidays excluded, the city will inspect the work to determine if it has been constructed in a satisfactory manner and to determine if all facilities are cleaned of construction debris that could be flushed into the city's sewer.

    C.

    No wastewater shall be discharged into any sewerage facility tributary to a city facility prior to obtaining inspection and approval of sewerage construction by the city.

    D.

    Following satisfactory completion of construction, the city will issue a construction inspection certificate upon request.

(Ord. 217-78 §302, 1978).